A seasoning and distribution system for a crisp production facility in Belgium


Case Study Description

Project Objective

Install and process a seasoning system for the manufacturer’s crisp production facility in Belgium.

Project Scope

The manufacturer is a long time Blackrow client who appointed us to install their process and seasoning system for their crisp production facility in Belgium. This included the installation of an 8 bay packing distribution system comprising of 3 lanes approaching weighers from opposing directions.

The challenges of this project were that the installation area sat within the food manufacturing plant, which works 24 hours a day including weekends. In addition the client’s working policy varied from Blackrow, allowing contractors to no work more than 60 hours per week, meaning we had to relieve our personnel each week allowing for us to adhere to the working time policy.

  • Installation of 2 Distribution Steelwork Platforms
  • Installation of 1 Weigher Steelwork Platform
  • Installation of 60 vibratory conveyors onto the platforms
  • Installation of 2 Washers
  • Installation of 8 Multi-head Weighers and Baggers
  • Installation of Check Weighers
  • Position of 1 Main Packing Panel at Platform level
  • Aluminium checker plate flooring fully welded on site
  • Stainless steel checker plate flooring fully welded on site
  • Water (Sinks/Washers)
  • Compressed Air (Gates/Bag Makers)
  • Nitrogen (Bag Makers)
  • Vacuum Pipework (Bag/Box Makers)
  • Installation of 3 Intralox Elevators with Guarding
  • Installation of 3 Transfer Vibrators
  • Installation of 1 Fixed Position Flavour Drum
  • Installation of 3 Flavour Elevators
  • Installation of 3 Flavour Applicators
  • Installation of 3 LIW Unit Platforms
  • Installation of 3 Oil Spray Lance
  • Installation of 3 Flavour Feeders
  • Installation of 3 LSU Tank under the Platform
  • Installation of 3 Seasoning Skid Steelwork with access stairs
  • Installation of 3 Flow Weighers
  • Installation of 4 Transfer Conveyors
  • Installation of 2 Divert Conveyors
  • Installation of 1 Moisture Reject Conveyor
  • Installation of 1 Cooler Outfeed Conveyor
  • Installation of 11 vibratory conveyors onto the platforms
  • Installation of Pneumatic Piping

What many couldn’t have predicted is that this project would have to be completed under the confines of the COVID-19 global pandemic, a first for all those involved. Safety is always paramount when carrying out on and off-site works but even more so in these conditions which required the team to allow for social distancing, increased hygiene measures and adherence to Government guidelines.

To ensure the safety of all involved the following measures were put in place:

  • Site safety team implemented negative COVID-19 tests before entering the site (These where carried out by the safety team)
  • Regular updates and briefings involving the entire team, ensuring specific instruction was given on how to operate and what PPE was required
  • Documented RAMS packs were provided which gave details on how to reduce the risk of the virus in various workplace situations
  • Increased hygiene and PPE measures, and social distancing

Because of these measures, Blackrow Health & Safety Team and the clients Health & Safety Advisors, we are pleased to report there were zero incidences of COVID-19.

Not only was the risk of Coronavirus managed, but the project was delivered with no delays.